Busy Busy Week, Finally made it to market day
Finalised run sheet
Finalised and Placed order for furniture
Setup for market
Market Day!
Mon-Ambassador meeting
-Ordered furniture with Anna
-Sent out email with market board, stuff with market board
Tues- Set-up furniture run sheet etc
Weds- Market day
Pack down
Team Palazzo – Creative Industries
Tuesday, 14 October 2014
Last class documentation
15/10
Today we met before the class just to write team reflection sheet
and this is the last shout from me :)
"Hey guys congratulation for winning the prices!.
Thank you for all the hard works and enjoy your summer!."
2014 TEAM 8 LOGISTICS
Sunday, 12 October 2014
Furniture Request Preparation and Document.
Wednesday, 8 October 2014
Returning furniture
8/10
So Our logistic group was busy running cleaning time sheet on the market day.
Each of us did our role
Unfortunately I haven't got photo of 10b12
but Luke was in charge of arranging tables in 10B12.
I was in charge of arranging tables back in order for 10b05 (industrial building).
I had to look at this picture..(because i couldn't remember details)
Rachel was in charge of taking back everything back to Tgarden.
but all of us were busy shifting tables and chairs back to the places..
and if others needed hand we helped them to run cleaning sheet smoothly.
After Emma left at 12pm Ben took over the management job and he ran the sheet.
Thanks everyone for participating!
_Minjoo
Tuesday, 7 October 2014
Runsheet in Action
Tuesday night for setup, our run sheet was finally put into action. Construction managed to finish building all of the stalls the night before, the dark space teams were making great progress and most of the large stalls where makers teams created their own structure were in place.
Once the furniture was all set up at 5pm teams started setting up their own individual stalls. Every hour Ben and I went around to all of the teams to make sure they were there on time, that they had all of the furniture they needed and if they needed anything else e.g technical cords etc.
Most teams stuck to their allotted times which was great and all in all it ran surprisingly smoothly.
Ben and I stuck around until 11pm along with the Market Board and other facilitators, in case any one needed anything and to help out.
Industrial design building layout for furniture
7/10
Industrial design building Layout for furniture
Evidence of industrial building layout before furniture moving.
This is how it has been laid out (what a lovely drawing..<)
This is how it should look later on as well!
so we had 5x Wooden long table
1x Small table
4x white long table in the room
I will make sure
we return everything back to where it has been.
Week 10 Summary
Individual ambassador meetings with the market board
Finalising all details tinning up loose ends
Started a new furniture document with more details sent out to all team to do urgently
An urgent meeting was held on friday to discuss matters such as Capacity etc...
Finalising all details tinning up loose ends
Started a new furniture document with more details sent out to all team to do urgently
An urgent meeting was held on friday to discuss matters such as Capacity etc...